Steel Spine for the Earth Sheltered Home

0

Posted on March 28, 2015 by

Big Picture

Tower_MichaelArcherAt the moment, the construction schedule has 3 main paths.

1) On the east side, we are getting the steel arches rolled.  We can start to erect those after the excavator comes in and sorts out the grading issue, but they are waiting on the frost laws to allow them to carry their heavy equipment on the roads.

2) On the west side, I am getting the Quonset hut ready as a work shop to build the wooden forms for the precast concrete ribs.

I probably have a months worth of work on each of these sides before the paths converge on the middle.

3) In the middle of the house, I need to get in these steel posts that will support the ring beam that will eventually support the precast concrete ribs that will eventually hold up the steel arches and shotcrete that will form the radial vaults.

This weeks video is about setting up the posts for the center section.

 

The Video

The Story

I’ll put the story in here to provide a little more detail and to make it text searchable for Google ;^).

Working backwards:

In this region of the earth sheltered house, the load from earth above (not shown) is directed, by the radial vaults (made of heavy shotcrete over steel arches), down onto the precast concrete ribs.

Tower_3D_1

On the outside edge of the house, these radiating concrete ribs (which weigh almost 5000 lbs each) are sitting right on 4’x4′ concrete pads made of strong reinforced concrete 1 ft thick.  However, at the middle of the house, the high end of these ribs are set into a central tower made of shotcrete (which will carry most of the final loads) over a steel skeleton (which will carry all the loads during construction before the shotcrete is in place).  This image also shows the QuadDeck ICF floor forms. When concrete is poured over these, it will help lock the steel posts into position.

Tower_3D_2

The load of those 10 heavy ribs runs thru the ring beam and down the structural steel columns into the shotcrete basement wall below.

Tower_3D_3

Tower_WallSurfaceThe 3D CAD model shows a nice flat surface where these pipes attach to the top of the basement wall.

The reality is that the shotcrete guys did not do a great job of squaring off the edge of this wall, probably because it was 9 ft tall and hard to reach. I needed to fix that.  I setup some cardboard forms to the level the wall should be at and backfilled with hydrolic mortar.  It was thin enough that it was pretty much self leveling.

The next step was to prepare the steel bases.  I bought a box of scaffold bases for $4 each, but the (nail) holes were too small to fit the anchors thru.  I drilled them out using the lowest setting on my drill press and some lubrication.

Drilling steel requires low speed and lubrication.  I lubricated with thread cutting oil.  The smallest container I could find was much more than I would need and only cost ~4$, the drill bit was 7$, so I used the lubricant generously in order to preserve the life of the bit.  I found applying it directly to the bit was the best way.  If the bit started to smoke, I would stop the drill and add more oil.  If the speed/pressure and lubrication are correct, long spirals of metal will come off.  This indicates that the steel is being cut and not just wearing away the bit.

 

RED_HEAD_SleeveAnchorThen it was time to head back out and mount the bases to the wall.  I was using sleeve anchors that require you to drill a hole first, and then drop the anchor in the hole.  It is important that the sleeve be completely below the surface. When you tighten the nut, the sleeve is expanded and presses against the sides while the nut pulls what ever you are attaching down toward the sleeve…   I was in a rush and didn’t put one of the first anchors in properly.  There was probably dust in the hole.  But I couldn’t pull it out again either.  With the sleeve too high, the nut tightened against it before pressing the metal to the concrete, so it would never be tight.   Eventually, it will be under another ft of concrete, so I was not too worried about it, but I put the rest in more carefully.

I was also careful to make sure each scaffold base was level so it would be easier to plumb the columns later.

My steel posts were ready a couple days earlier than promised (a first for me on this build), so I picked them up in my trusty trailer.  They weighed about 100 lbs each and put the trailer near its official limit, but it felt like it pulled easily.

Tower_Trailer

The following weekend, my parents visited with my sister.

The mission was to move the steel posts into position on the base plates, hold them steady and level and then tack them into place with my welder.  The first one worked pretty well.   But the welder jammed on the second one.  I couldn’t untangle it, so we had to cut out all that welding wire and re-setup the machine.  From then on, I always checked the wire spool every time I moved the welder to make sure that it was not tangled.

Tower_JammedWelder

This third post was the one on the less stable base, so we added extra bracing to keep it plumb until the concrete is poured around it.  We had a lot of experience pluming steel last summer, so everyone knew exactly what to do and it only took a minute or so.

My sister and I both enjoyed the welding, so we took turns welding vs holding… Some times on the same post if it was tricky to access a certain point.  The most time consuming part of the process was simply adjusting the scaffolding, etc. so we could reach what ever we needed to reach.

Tower_Welding

It took us about an hour to get the first 5 posts in, but they were on the side of the circle that was easy to reach.  We were expecting the back side, were we had to balance on the wall, to be more difficult, but it was pretty easy too.

Tower_Welding_3

After all the posts were in place, I was worried that someone may give these a good push and cause them to shift… Yes, they are welded to steel plates bolted into strong concrete with 3 inch steel anchors, but an 8ft long 100lb lever would probably be able to pry those out.

I wanted to weld the ring beam on right away, but each half was 320 lbs and I couldn’t think of a safe way to get them into position.

Tower_HeavySteel

So we decided to weld some rebar between the posts as a temporary solution.  This was nice and easy and I really liked the look of it, so it will be sad to have to cut most of it off again when we need to put the door bucks in.

Tower_Welding2

I was not sure how far my tank of shielding gas (Ar and CO2 for the MIG welder) would go, so we only did tack welds.  That turned out to be a good decision because it ran out just before we were done.  Without the gas, the final few welds looked pretty ugly.

After that, we put in some work prepping the shop for building the forms, and I will talk about that another time.

The next step in this center section will be getting in the QuadDeck ICF (insulated concrete form) floor over the basement.  I am having a painful time getting that scheduled.

The rest of the steel arches are still being rolled and I will soon start on the forms for the ribs.

 

GoPro vs Wingscapes timelapse camera

1

Posted on March 16, 2015 by

Here is the video…

And so the text would be searchable…

I got my Wingscapes Timelapse Cam years ago when I first bought the property… Originally, it was that so I could trace the shadows moving across my lot (important for passive solar positioning), but I ended up enjoying recording the construction process with it also.  Lately, I have wanted a better camera.  Eventually, my whining paid off and my wife got me a GoPro Hero3 for my birthday.  “White” just means that it is at the low end of the GoPro video range, but it still has the timelapse feature that I wanted.

For a comparative test, I mounted the two cameras side by side and recorded some timelapse footage for an “odd job” that I did (see the video link above).

The “odd job” was building a giant wall out of bales of rigid insulation… Why? I wanted to put a tarp across the back of the Quonset hut to stop the wind from blowing thru.  This would allow me to use the garage as a workshop…  But it was like a wind tunnel in there and I couldn’t keep the tarp still long enough to bolt it on…  I had these bales of rigid insulation already stacked somewhere else on the property, and I decided to restack them at the back of the quonset hut to block the wind…  It worked very well, and I chuckled at the idea of having an R-value of ~240.  At some later point, I will put up ICFs to form a proper wall, but I imagine even that would have been difficult in the wind tunnel environment of that quonset hut…

 

Anyway, let’s compare…

Wingscapes Pros:

Much better battery life (days or weeks with 4AA batteries) and better time lapse options for longer duration’s (10 seconds to daily)…

This makes sense because that is what it was designed for.

Wingscapes Cons:

A tiny pinhole lens in a large heavy housing that can be a challenge to setup.  It also has manual focus (that I have messed up a few times) and a basic, but awkwardly placed, view finder with no way to really tell how the shots are coming out until you download them.

I really can’t understand why the wingscapes cam needs to be so bulky or why the birdwatchers who buy them don’t demand better optics.

WingscapesVsGoPro_03

GoPro Pros:

Much better optics, plus its lens is very wide angle, which will help with the interior shots later.  The GoPro is also much smaller and easier to move around.  The GOPro settings can actually be controlled from my phone and my phone screen actually works as the view finder (which I thought was really cool until I realized how quickly the wi-fi used up the battery).

The timelapse options are actually better on the low end of the range…  With a number of options between Half a second and 60 seconds…  It also has much better Video options. Even though mine is just the white edition, it gives HD up to 60FPS.

And this all makes sense because this camera is meant to be strapped to an adrenalin junkie and pushed off a cliff.  Its timelapse options are more intended for capturing a half hour of sunset than a day at the build site.

GoPro Cons:

The battery life is poor (for a timelapse).  It can do 3 hours of video at 60 FPS, so I expected that it could go for ages on timelapse at 0.2 FPS, but it didn’t make much more than 4 hours, (even without the wi-fi viewfinder turned on, which drains the power even faster)…  And when the battery dies, it is a special GOPro battery, so I can’t replace it with a spare.   Also, the color seems less vivid on the GoPro, but I have only tested it on grey days and with pretty grey subject matter

WingscapesVsGoPro_01In summary…  I don’t plan to get rid of either camera.  They each have their place and will help me catch good footage and we try to get this house built over the summer.

(Temporary) basement stairs

2

Posted on February 21, 2015 by

2015-01_WinterPanorama

 

 

Its cold out there:

Due to our cold Michigan winter, construction on our earth sheltered home had to slow.  Concrete (my primary building material) would have frozen before it cured.  There are additives that will speed up the cure, but they are corrosive to steel, so we just have to wait.  I guess perhaps this is one of the reasons that stick frame construction (wood) is so much more popular in this frigid area. Framing guys keep right on working in the cold (although it is probably unpleasant).

2015-01_WinterDriftsInstead, I have kept busy with a number of small jobs (and prepping for future jobs).  I have several “stories” in progress.  One of the things I could do was put in some temporary basement stairs.

 

 

 

For those who want to skip to the video:

The Story:

Since these stairs would be exposed to the elements for a while and eventually replaced,  I dug thru the scrap wood pile for some junk boards to cut to length as treads.  This snow covered pile was the worst of the wood left over from forming the footings.  This was junk wood that my wife wouldn’t even let me bring into the Quonset because she was concerned that the mold would spread to the “good” junk wood.  But I couldn’t just throw it away.  I figured I would use it for something rough and temporary, and then again as camp fire wood.

2015-01-24_StairTemplateI had already mounted the tread brackets to the shotcrete walls.  This was done with the aid of a template (also made of scrap forming board).  I screwed the template into the lower tread to position the higher tread and worked my way up the wall.  Actually, by also fastening the upper tread to the template, I was left with free hands for drilling pilot holes into the concrete for the screws (and for taking this photograph).

By the time I started recording the video, I just had to trim the treads to fit between the rough walls.   I actually had a pile of screws that I had taken out of the formwork and bracing when I disassembled it, and was able to reuse all of that also.

2015-02-07_StairDeckThere is actually another foot of wall that will come when I pour the floor over the basement, so there will eventually be a couple more steps.  But in the meantime, I put a deck across the top.  Since this is all temporary, it seemed easiest to just span the top of the walls.  On the drive home that night, it occurred to me that the quad deck will need to be set on top of on of those walls and I will soon need to move those boards out of the way again.  I should have done it properly by mounting horizontal boards on the wall and spanning the deck across that.  Then the tops of the walls would have been clear for the Quad deck.

That first day, I measured up for the last 4 stairs, but then I got distracted by other tasks.

I came back on a warmer day with finishing these stairs on my list (along with preparing the tower base and some other jobs).   I had the rough sizing and a vague plan in mind when I showed up, but I basically ended up just doing a quick re-measure (without writing anything down) and then rough cut the boards (eyeball-freehand on the table saw) and just screwed everything together.  To keep it square, I did some rough measuring to make sure that the width was the same at several key points…  Any true right angles are just luck, but it feels level and secure and will do the job.  The video shows that I didn’t remember all my measurements correctly because I had to trim nearly 6 inches off the back legs for a decent final fit, not really sure what happened there, but better too long than too short.

This last section of stairs needed to be both temporary and removable.  I plan to lift it out of the way when I pour the basement floor.  After the floor is done, I can trim off the bottom 6 inches and place it back again.  After the area is all closed in and safe from the elements, I can pull out these junk steps (firewood) and replace them with something that wouldn’t make a carpenter cringe so badly.  Not sure if I will have time (at that point) to make the final stairs myself.  Lets wait and see if I am critically short on time or money at that point.