Front Steel Columns

In this segment, we mark and place the front columns and the curved I-beams that form the framework for the entry and green house sections.  Most of the time-lapse footage was lost some how, but I did have some pics…

The video

Surplus Steel

I bought the columns from the surplus steel place in my area.  The cost was low enough that I didn’t mind a few imperfections.  No regrets and I will probably do it again.  I did put tape over the holes to keep wasps from moving in.

Trouble with the Forks

When I bought the skid steer, the guy who sold it to me said he also had a beat up set of old forks that I could have for 200$.  New forks cost 3 or 4 times as much, so I told him to send those with the skid steer even though I hadn’t actually seen them.  At first, I just noticed that the back board was a bit damaged.  After using them, I also noticed that the two forks were actually different thickness (miss-matched set) and had bent slightly differently and I was having trouble holding things level.

We didn’t worry about the back board, but my father and I fixed the “uneven” issue with some torches (and lots of patience) to heat up one of the forks so we could bend it to match the other.

But all that time, I was using the forks to lift heavy things, so I didn’t notice the 3rd issue…  When you apply loads the other way (pushing down on the forks), the locking mechanism is supposed to hold them in place.  However, the top ledge that holds the locking mechanism in place had been slightly stretched upward and increased the tolerance by maybe 1/4th of an inch, and that was enough for the mechanism to actually detach when the load was pushed the other way.

While setting the second I-beam, The beam got hooked on the bent back shield and wouldn’t let me lower the forks.  Since this flipped the load direction, it also shifted the locking mechanism down 1/4th inch relative to the forks and they detached from that top edge.

With the load direction reversed, the forks detached from the skidsteer

Those Forks are a few hundred pounds of heavy steel, so rather than just let them fall off and possibly damage something on the way down, we strapped them to the quick attach mechanism on the skid steer so we could still lower them carefully.

The final fix was to weld 2 pieces of angle iron across the top of the quick attach mechanism to remove the gap so it won’t be unlocked by a reverse load.

Final view. There will be windows under most of those Ibeams and a Front door under the left most one. Earth covered in grass, etc. will be above.

Making and Setting-up precast concrete ribs

These concrete ribs were designed to give me more of an open space feeling without needing to build a wide and tall vault.  For more about the design of the ribs or how I made the forms, you can read this earlier post.

This was really an epic part of the earth sheltered home build project, spanning (no pun intended) much more time than I would have liked.  The costs for the forms and concrete were pretty minimal, the majority of the cost was actually in hiring the crane to move them around and set them up.

The view from below after the ribs were setup.  This is our "open concept" living room...

 

Side note: since I am so far behind…  I will probably go and improve the section on the timeline next. Thanks to those of you who wrote to inquire if I died.  Nope, just really busy and didn’t have time to put a video together.  Speaking of which…

The Video

Lessons learned

  • The Pump truck did not make things easier.  Pump trucks are expensive and I needed it to come out for the floors anyway, so the first few rib pours needed to be coordinated with other jobs.  This complicated the planning and made the pour days harder.  It also slowed down the progress on the ribs by delaying the pours.  And after all that extra planning and delay and expense, it was just plain harder to fill the ribs from the pipe than from the chute because it was really difficult to move it around.  I guess my advice here would be to talk to the concrete guys and ask them how they would recommend you handle it.  It was probably obvious to everyone except me.
  • Originally, I used silicone caulk to seal the bottom edges of the forms against the floor.  However, this was a pain to clean up later.  For the 2nd set, we used play-dough that my wife got cheap on clearance somewhere.  The play-dough came up easily enough at the end, but it was such a pain to roll out and put into place that we ended up going back to the silicone for the later ribs.
  • The first set of ribs took about 4 hours per side to polish.  I would start with a diamond cup wheel and then follow up with successive polishing pads at 50, 100, and 200 grit.  I also used a special wheel to put a 3/4 inch round on the edges.  For the second half of the ribs, I got a larger, more aggressive diamond cup wheel.  It worked so well for the first step, that I quickly did all the other ribs.  It was only when I got to the 50 grit pads that I noticed the diamond cup wheel had made deeper scratches than the previous one and it was much more difficult to remove them. I even went back to try the less aggressive cup wheel once I realize that the 50 grit was not working well. Overall, this mistake cost me several extra hours for each rib.
  • The moving dollies were supposed to be able to handle 1000lbs each, but that was clearly an exaggeration.  I used more than 10 for each 5000 lb rib and still we had crunching sounds as their ball bearings exploded out all over the floor.  The tires on some of them shredded completely.  Eventually, I learned that most of the damage happened as each wheel rotated into the correct position to roll forward.  By the time I got to the 3rd set, I had learned to point the wheels all in the right direction before lowering the rib on to them.  This increased the survival rate considerably.  I also salvaged partially damaged dollies by consolidating the less damaged castor wheels on to other dollies.
  • The rubber form liner molds were an interesting part of the build for me and I like the final look on the ribs, but again, not the best idea.  More details below.

 

Liquid Rubber Form Liners

Originally, I planned to use the Styrofoam ceiling tiles directly, but after handling them a bit, I was worried that they were too fragile and wouldn’t last thru multiple uses.  I also thought it would be a bit tricky to place them in the form so they would be centered because they were a bit narrower than ideal.  However, if I used the ceiling tiles to form durable rubber form liners, I could get longer pieces that would be reusable and would be the inverse of the tiles.  I could carefully center them on a board of the right width so the full depth forms could be easily placed, etc.  I did some math to find the volume that I would need and found that I could get the PolyTek 75-75 ingredients for about 175$.  That seemed reasonable enough to me at the time.  The box of foam tiles was about $40. However, I soon discovered that mixing carefully was critical.  My first few attempts were mostly good, but 95% isn’t good enough to cast concrete with.  I only ended up with enough decent panels to do a small section of the first few ribs.

For the living room ribs, I decided to make the panels a little thicker (these were the ones I showed in the video). I would need to order more liquid rubber.  This time, it was more like 225$, so I was in for roughly $400 worth of liquid rubber.  That would have been enough to buy new Styrofoam tiles each time, so not the smartest move in hind sight.

I didn’t quite use up all my liquid rubber ingredients on the panels because I decided to try the Styrofoam ceiling tiles directly on each alternate rib.  This way the pattern inverts, positive/negative for each rib.

 

Cost and timing

See the other page about costs for the forms, but they were just a few hundred dollars and were reused for all the ribs.  So divided by 11 ribs, that is just about 30$ each.

The rebar was fairly affordable also.  We used about 60$ worth of #5 and about 50$ worth of stirrups, so about 110$ per rib.  There were also some steel plates that I built into the ribs and I think I paid about 10$ each for those from the scrap yard.  Tie wire and welding costs are hard to guesstimate, but lets say it is less than 5$ per rib.

The concrete was about 1.3 yards per rib, which would be less than $185, even after some waste (Concrete costs about $100 per yard, delivered, but there are a couple other charges).

The molds and ceiling tiles were about 450$ total, so about 40$ each.

Then I bought about 20 of those little moving dollies and some other miscellaneous stuff for about 220$ total, so 20$/rib to move them out of the garage.

The grinder and all the pads were under 220$, but I still have the grinder many of the pads, so I am just going to leave that stuff out.

So lets say the total was $400 per rib.   Not bad considering the quote to have it done by someone else was about $8,000 each.

Unfortunately, the crane and welding the ribs to the ring just about doubled that cost.  The guys from RTC were great to work with and I appreciated their help, but I had not budgeted enough in that area.

2016-08-28_Cost&Time

Timing varied as I got better at each task, but here is the rough break down in man hours.

Form prep took about 2 hours per rib and includes cleaning the form segments, fixing any damage, re-assembling the form and attaching it to the floor, and then caulking the bottom edge.

Rebar was next and was taking about 8 hours on average, including getting all the rebar in, tying and welding.

After the rebar was in, I needed to call for an inspection, which didn’t take much time, but did delay the next step.

Next was the pour.  It actually took less than half an hour to pour each pair of ribs, but then we would spend at least an hour or so troweling and finishing it off.  Lets be generous and say 2 hours per rib.  Then there was some delay (several days to a week) as we let the concrete cure.

Then we would spend about 6 hours (3 hours each) unpacking and moving the ribs out of the way. This included a lot of clean up.

And then the cycle could repeat.

After the ribs were out of the garage, I could polish them.  The first half took about 4 hours per side to polish, so 8 hours per rib.  But, thanks to an overly aggressive cup wheel and adverse weather conditions (hose freezing, etc), the second set took about twice that long.  Lets put in an average of 12 hours per rib.

The flip and setup time wasn’t too bad, but lets write it down as an hour each there.

This brings the total hours per rib to about 28.  I had 11 ribs to make, so about 308 hours total.  If I had done those in 40 hour work weeks, it would have been nearly 8 weeks of constant work (yes, some of those hours or days were worked by other people like Sherri, Bonnie, Aaron, Dan, John and Mark). However, I already had a full time job, and also had other things to work on at the house, so I ended up spreading this part of the build over a whole year.  The video on this article covers from July 2015 thru April 2016.

Needless to say, I am glad the ribs are all done.

Gallery

After a long and difficult project, looking over the pics feels pretty good.

February 2nd

Virtual Build

Over the past couple weeks, I put in half an hour here and there in the evenings and moved the virtual build slowly along.  Of course, I would be thrilled to get this virtual build speed in the real world ;^)  Initially, the plan was just to illustrate the building process for various subs that would be helping.   I planned to just show the construction of the basement, central tower and how the ribs would be setup.  However, as you may have seen over the past couple posts, the virtual build has already helped find and solve so many problems that I have decided to press on with it.  I added the garage and I am currently working on the bedroom wing.  Next, I will work on the front of the house.

Virtual build as of Feb2nd, the garage, mezz and other areas are mostly complete, I am working on the bedroom wing and will work on the front of the house later.

Virtual build as of Feb2nd, the garage, mezz and other areas are mostly complete, I am working on the bedroom wing and will work on the front of the house later.  You can already see that this house design is very original.

I had been thinking a lot about how to lay out the ribs while I was casting them, I thought it might be a good idea to illustrate that with the virtual build.  For a long time, our plan has been to pour the garage slab early in the build, but only setup the rear of the quonset hut.  I could use the partial construction as a covered workshop in the back while I setup the rib forms on the front half of the slab.  Without the roof in the way, I could use a crate to lift the 4500lb concrete ribs up and over to where they would be set.

I had planned to make a left and a right rib form because it would save me needing to flip and polish the “back” side of one that would be exposed against an end wall.  I had already worked out (mathematically) that I could fit two of these on the slab in front of the partial quonset.

Gantt_RibsNow I was working on my gantt chart and considering how much time would be taken making these only two at a time.  I also considered how much extra cost would be incurred with the multiple crane visits (to set them up 2 at a time).  We had already planned to put a slab in-front of the garage (even if the rest of the driveway will be gravel), so the boys could play basketball.  I started considering the option of placing the slab earlier in the process  and building a few more forms.  Even if the extra forms cost an additional 600$ each, I could make 2 more and save on 2 expensive crane visits and a couple weeks of time.  I would probably at least break even on money, but save time.

There would be no additional cost to adding the concrete pad early since it was already planned for later in the process, but it may later be seen as “in the way” as construction equipment would need to be careful not to crack it…   

ArchForms_Layout1So, I added the ribs to my garage model…  You can see that it would be very difficult to fit a 3rd rib on the pad.  Yes I tried other configurations, but I need room for the forms around the ribs and space too work, and I couldn’t let them go under the quonset or the crane wouldn’t be able to lift them up without dragging them.  However, for the other ribs, I decided to make two left hand ribs and they can be put closer together…

Then it occurred to me that I needed to go back and reconsider my earlier decision about wanting to start with a left and a right rib to save time/money polishing (because one side would be placed against a wall.)  I decided that I would save more money and hassle with the more compact arrangement of same-side ribs.  In the software, it is pretty trivial to make the necessary changes and voila!  Four ribs in a compact arrangement on the one slab.

ArchForms_Layout2

 

I will update the Gantt to show building two forms first, then working on the second two forms while the first two ribs cure…  Then I could position all 10 ribs in only 3 crane visits instead of 5.  Of course, I still need to polish the back sides of the ribs, so I will need to flip them over before I set them, but I can place them in the (soft) dirt for that and I think I can get that done with only one extra crane visit for the full set.  It seems like a plan for now.

Other revelations included that the steel stud layout for the bedroom was messed up by the architect (yup, I checked my original notes).  It was a classic symptom of 2D design where the various views, created separately, were not actually compatible or build-able.  I went back to check my original notes and sketches that I had sent in and they were correct, so I guess the architect just didn’t understand.  I will document that another time.  Lets just say my errata list is growing.

Sourcing

I have started hearing back from various contractors and the bids are looking much better.  I got a very reasonable excavation bid to go with my good footings bid.  I got bids on hooking up my electricity (a very reasonable $285 to setup the temp construction meter and then about $4.60/ft to run the permanent cable and setup for 400 amp service.  I am waiting on an electrical and HVAC update that should be in early next week.   It is clear that I still need to find a reasonable plumber bid (the 6 I got last year were all either too high or too un-reliable).

I also got prices on HDPE pipe for various diameters…   Trying to understand the pricing structure better, I divided the price by area, weight, etc. and quite reasonably, it turns out to be priced by weight.  $1.25/lb, delivered.  For 8 inch pipe with a 1/4 inch wall (HDPE 8″ DR 32.5), that comes to about $3.83/ft.  I need about 450ft for an earth tube loop, plus about 350ft for internal duct work in the house…  So that goes into the estimates.

Shotcrete meet

A highlight of last week (for me anyway; I am not sure how your week went ;^) was a meet with my most-likely shotcrete guy.  I have been talking to a couple other potential shotcrete contractors, but one is just not big enough scale and the other is not really sure about the whole earth sheltered concept.  At this point, I trust Nate more than the others and I think his prices seem fair.  The biggest problem is that he is hard to get ahold of.  It has been more than a year since we managed a meeting.   My project is just too unusual for him to quote confidently, so he had agreed to a time and materials quote, but I needed a better idea of how long he thought things would take and I still hadn’t got a quote on some aspects of the build, such as the specfinish on the inside.

I drove out to his place, which is about an hour from my current home and about 40 minutes from the building site (its a big triangle around Ann Arbor, MI).  He had a couple big friendly dogs and a nice sized kitchen table to lay the plans out.  I set up my computer and showed him my virtual build, my Gantt chart, etc.  My main goals were to make sure that the plan for the build made sense to a professional and experienced shotcrete guy and to get good numbers for budgeting purposes.   I showed him the virtual model and we talked about practical things like how to get the rebound (shotcrete that doesn’t stick to the wall and is, therefore landfill) out of the basement.   We talked about the possibility that some of the non-load bearing walls could be built hollow (or filled with insulation) and still covered with a thin coat of shotcrete to match the more solid walls.  We talked about hiring some of his guys to help tie the rebar (along with other tasks), and how quick they could work.  He even shared some trade secrets about the fastest ways to tie rebar, plaster walls, etc.

Along the way thru the virtual model, we kept referring back to the Gantt chart, which included things like the dates for each of the 4 shotcrete phases and the amounts of shotcrete that needed to be applied in each phase.  He factored in if  it was high work or regular walls (which he kept referring to as “money walls”), etc.  We discussed if the dates were good for him.  He was a bit concerned about the first shotcrete date because it was in May, which is prime swimming pool season.  The other dates are past swimming pool season, so he will be glad to keep his schedule busy.

We discussed equipment that I would need to rent and what his crew would bring (and the associated costs).  No surprises there except that he mentioned he would bring lots of scaffolding at no additional cost, he just wanted me to make sure the floor was level enough to move them around.

We discussed how much notice I would need to give to schedule his crew.

The main rough patch came when I got to the part about using his gunite machine to spray the specfinish along the underside of the vaults.  Nate did not want to do that.  Apparently, it is messy horrible work.  See this pic from monolithic.org where they create inflated fabric domes and then coat the insides with shotcrete to form the structure.  Note the full body coverage including saran-wrap on the helmet.  When the operators face gets covered, he can pull on the roll to get a clean section.  My plan had most of the shotcrete structure applied from the outside and only a very thin (3/8″) layer applied on the inside, but still…

Nate  said he would rather just have his guys apply the plaster by hand, but that sounds rough and slow to me.   We talked about other alternatives including spaying on the ceiling with a drywall hopper gun or having an acoustic ceiling company come in and take care of it.  I had already got a quote on acoustical ceilings, but my wife didn’t like the samples I brought back and didn’t want to consider it at the time.

20x20GlueUpTilesAnother option may be that I would use the same glue up styrofoam ceiling tiles that I planned to use to form (impress) the ribs.  It may look good to have the same pattern in the vaults between the ribs, but I am a bit concerned about fitting the square pattern to the curved and radiating vault shapes and it wouldn’t work at all in the compound curved bedroom vaults.

I left the meeting with a few notes on minor changes that I needed to make to the Gantt and process and some homework to Google search a number of things that were discussed (such as a rebar tie belt with a reel).  I also have the costs I will need to complete this portion of the budget.

 

Year end

So the year is over.  It didn’t exactly go as I had hoped, but we are definitely in a better position to build next year than we were a year ago, more on that in my January kick off post.  It is a bit frustrating as I put off doing other things because we expected to build, but such is life.  This past month, I took things pretty easy.  I only called one person for a quote (a very reasonable sounding plumber that I will bug again in January), and I put some time into building the home virtually.

Virtual Construction

Virtual construction is a way to run thru the process of building without the huge expense.  I individually model each stud, track, buck and ICF piece and then assemble them as I would in the actual construction.  Along the way, I am thinking about sequencing and other assembly problems.  I try to build to the plan, but make notes when I need to make changes so things will fit.  Of course, the computer could make things a bit too easy, for instance, I could just array my studs along and have perfect spacing.  Instead, I tried to build things more manually by inserting and positioning each piece.

The below image shows the first steps of my basic construction plan.

I would start by pouring the footing, which includes a lot of precise layout, rebar, form work, etc.  Actually, once that footing is done, I will be much more relaxed for the rest of it.  I would then set the track (curved or straight) for my steel studs into the top of the footing with Tapcon screws.  Then I would place wooden window and door bucks to guide the spacing of the studs.  The Marinoware steel studs and steel frame jambs would be set (plumb) and screwed into the tracks.  Flat straps are screwed to the outside of the studs to increase the rigidity of the assembly.  Metal lath is screwed to the inside of the studs and track, partially to add rigidity, but mostly as a curved backing to catch and form the shotcrete.

Basic construction detail

Basic construction detail

Along the way, I spent a lot of time figuring out steel stud placement.  I am planning to use “balloon framing” so that load bearing walls will line up and I won’t need to spend as much time or money on laying the curved track.  Since the steel studs will just be fancy integral formwork, I don’t need to follow strict structural guidelines.  Instead of 2ft or less spacing, I can go a bit wider and not need to cut as many studs for windows, etc.  I can vary the placement of the studs to line up with windows and doors across the various levels. For instance, there is an opening directly above the basement opening (shown above).  If I shifted the main floor opening by a few inches, I could use one long steel frame jamb instead of needing to place two.  I could also align the guest bathroom door with a mezzanine window buck and simplify the framework there also.

 

After all the steel studs, rebar and conduit are in place, with metal lath to keep things stiff and catch the shotcrete, we would shoot the basement walls 8 inches thick.  Since the steel studs are 4 inches deep, this would leave 4 inches beyond the studs.  The rebar, just outside of the steel studs, would be nearly in the middle of the wall.

Even though many of the steel studs go thru 3 floors (balloon framing), only the basement shotcrete would be applied in this phase.  The top of this shotcrete wall would be cut/troweled roughly level six inches below the floor level.   We may even be able to set the column base plates in before the shotcrete sets completely.  We would then setup the steel columns and ring beam (I will need a crane of some sort) that will later support my concrete arches.  I may do a little MiG welding to tack things in place at this stage.

RingBeamSetup

Ring_Beam_Intersect_FixedRingBeam_IntersectThis assembly looked fine at first, but I later discovered that the ring beam intersected the door buck by several inches.  This was a mistake I had not caught earlier.  I decided the best fix would be to notch the ribs…  These thumbnails illustrate.

The floor system I have chosen uses ICFs (Insulated Concrete Forms) to support the concrete (instead of the wooden subfloor the architect/engineer specified, so yes, I will need to get this stamped by an engineer at some point, I was quoted $800 for that).  These QuadDeck ICFs have light steel joists built-in to reduce the number of temporary supports needed.  The ends will rest on the shotcrete walls with an inch or two of polystyrene overlap (roughly cut with a hotwire) and be tied in with bent rebar pieces.

Construction_Details_021

This next image is a detail of the rebar (shotcrete and other details are not shown for clarity).  Horizontal rebar is wire tied to the outside of the steel studs and should increase the stiffness of the formwork.  I considered threading it thru the holes, but that would probably be quite a hassle.  The vertical rebar is wired to the inside of the horizontal rebar, but with 8 inches of thickness, there is some flexibility here if needed.  Rebar is placed before the shotcrete, and then some pieces are bent down into the ICF channels as needed.  More can be added later and bent upward if necessary.  I anticipate some issues in certain locations where the QuadDeck spacing clashes with the steel stud spacing, but it should be manageable.  I also considered/modeled rebar placement between other ICF sections.

Rebar_Vertical

After the ICF forms are placed, they can be walked on.  The electrician and plumber should appreciate how easy it is to set conduit and piping into the ICF decking.  The ICFs are about 7 inches deep and we will be adding 5 inches of concrete on top of that, so there is plenty of room to work.  We also plan to lay radiant flooring across the top of the ICFs.  There are little plastic clips that screw into the polystyrene easily to support the radiant tubing.  We will screw a form to side of the wall to contain the poor.  It will only need to support 12 inches of concrete, so it shouldn’t be a problem.

ConcreteFloor

Some of you may need a cross section vertical to understand the quad deck floor properly…  Here it is.  Basically, the ICFs form the “negative space” so that the concrete forms a nT (like a single or double-T, but continuous) beam across the spans.  Where we meet a wall, the ICF is cut away so the concrete rests on the wall (tied in with rebar not shown here).  On the left side of this example, I have cut away some of the ICF in order to create a concrete cross beam above the stairs to the basement.  After the concrete is poured, the ICFs remain to provide insulation against heat and noise.  They will ensure that my radiant heat goes up.

QuadDeck_crossSection

 

Construction_Details_Additional_StudsNow that there is a floor to walk on, additional studs, conduit, bucks, etc. are added in preparation for the main floor shotcrete.  Since many studs penetrated from the floor below, this additional work is just incremental.  I have not modeled it all yet, but it will include the fill walls under the ribs, the walls around the spiral stairs, etc.  Once these walls are up, I will want to model the arches across the donut vault, the hop across the basement stairs, etc.

Here is a final look at how far I got during my Christmas break…

Construction_Detial_Dec2013

Worthwhile

Window_MissalignmentsWindow_Missalignments_FixedThis process has been interesting so far and has resulted in a number of small changes.  For instance, I noticed that the original plans placed the mezzanine windows such that the east one was right up against the east wall.  When I built the 3D model, I placed the stud so that it would be at the surface of the 8 inch thick wall, but realized that one of the 12 inch thick ribs actually intersected the studs supporting the window.  If I wanted to build the balloon wall before placing the ribs, I would need to move the stud by at least 4 inches to clear the rib.  I also planned to put in a 14″ sun tunnel thru that corner to bring daylight to the guest bathroom, and that would also have passed in front of the window… So I decided to move all the mezz windows over by 16 inches.  Since the steel studs were also framing main floor and basement doors, those would also need to move (to keep the steel stud layout simple).  In the computer, this was much much easier to fix than it would have been if I had discovered the issue during the actual construction.

Similarly, I decided to lower the basement egress windows by 6 inches, I added a door way in the basement, etc.