Buying the land, hiring the architect and getting all my permits were each big steps toward this earth sheltered home. But, digging a huge hole makes those other steps pale in comparison. Things are now very serious. Where I once had a nice green rolling hill, I now have what appears to be some sort of ecological disaster… Actually it looks a lot like a sand quarry. I look forward to restoring it again as soon as possible. There is no way to turn back now, I have to push through.
Prep
We only had to excavate the partial basement portion, just over one third of the site. The shape of the basement is like a half circle with a few bumps on it… Sherri and I started the day by staking out the perimeter of the footings. Then I had a chat with the excavators (Roe Brother Excavation). I had invited the footings guy (Doug Dysert of Dysert Concrete) to join the conversation so that the excavation would be done according to his needs. Since my footings are curved, he had already told me that he would rather have the excavation down to the bottom of the footings (easier to build curved forms on the ground rather than dig them out). But now I wanted his input on how he planned to create the step footings that would transition from the full depth basement footings to the slab on grade footings and how that would affect the excavation plans…
Doug said he didn’t like engineers “sloped” step footings. He said, “Maybe that’s how the specify it on government jobs, but that is not how we do things around here.” He would prefer that we build the basement footings and walls first and then back-filled before working on the slab on grade footings. I was concerned about building footings over fill and about making any changes that the inspector wouldn’t like. Doug said I should make sure the inspector likes those footings and everyone agreed my sand would compact very nicely. Doug also sketched me his plan for connecting the basement footings with the slab on grade footings. The next day, I took those to the inspector, more about that in a separate post.
Anyway, back to the excavation… Doug didn’t want a sloped excavation, but I was concerned about needing slope for the footings specified by the engineer. We agreed that a “double over-dig” would be OK. We would over-dig 4 ft around where the footings would go, and then step up 4 or 5 feet and then over-dig a second 4 ft out from the first. I figured it would give the shotcrete and waterproofing people space to work and would allow me to easily excavate for sloped step footings if I needed to. Even if it crumbles, it is essentially a 50 % slope, so it should be OK. Doug sprayed the 4 ft offset line (curving) around my original basement footing stakes so everything was marked out.
My favorite quote of the day (paraphrased)… “The problem with dirt is that is is all in the wrong place. For instance, here we have some dirt where there should be a hole. Some times you have dirt where there should be water. An excavators job is to fix these mistakes.” I would add to that every earth sheltered home owners fear… “Some times there is water where there should be a hole”, fortunately, that is probably not going to be an issue for me on this sandy hill site.
Dick Roe (an original Roe Brother) got thinking about how to approach the dig (you don’t want to dig your self into a corner) and Marty (a Roe Son/Nephew) got busy on my drive way. Meanwhile Sherri did the smart thing and quietly added center-line stakes well beyond the excavation area.
Lesson learned
We had made things hard on ourselves by outlining the curved project with curved offsets. Once the excavation got started and the stakes were dug out of the hole, it got harder and harder to remember what was going on. I couldn’t visualize it anymore and I have been staring at the plans for years, so I am sure my excavator had no chance. The hole ended up looking somewhat like an amoeba as the excavator tried to dig just the right amount, but not too much. It was also a challenge to deal with the growing piles of dirt around the hole
My excavator was kicking himself for not laying out the overdig with a rectilinear shape (like a trapezoid) around our curved plan. He would have been able to stake out the overdig easily and then dig it out with much less time spent scratching his head. Make sure to tell your excavator “the footings may be curved, but the excavation is all straight lines.”
The Excavation!
Here is a video of Sherri and I laying out the basement stakes and then the digger getting to work.
With the extra head scratching and time spent on my driveway, etc., they didn’t manager to finish the excavation on day 2. They came back the following morning and took care of it. By the second day, the excavator had decided that the site was too sandy for stepped sides and put in a slope for most of the way around (which is what I had originally asked for). He also added a ramp to make it easier for us to get in and out of the hole. He said that if Sherri and I found it was too small, he would come back and make some final adjustments.
Well, it has begun! I will finally be telling my friends about this site so they can follow along. I also created a parallel Facebook page for those friends and family who always stay in Facebook. It also lets me have this cool “like” button on the right hand side of the screen. Since I plan to record and upload videos, I also started a channel for “Simon@HomeInTheEarth.com” on Youtube. I uploaded my first video here…
Excavation, day 1
Excavation, day 1
We still have not closed on our loan, we don’t even have a closing date (we have had 3, but currently don’t have any). On the other hand, construction season is passing us by, so we decided to go ahead with the excavation.
We ended up going with Roe Brothers Excavation. I liked them personally, I liked that they met with me when they said they would and they got me a quote like they said they would. I also really liked the quote. I liked it so much, I was a bit concerned about what I would discover from the references. I was quite relieved when all the references came back very positive. I asked each reference when Roe Brothers had worked for them and they all said, “just a few weeks ago…” It actually took me a week to getting around to calling them, so that is a really good sign that they weren’t cherry picking their references.
Roe Brothers showed up right on time, actually, I got Marty, not sure if he is a brother or a nephew. I’ll ask him next time I get a chance. First, Sherri took care of the initial paperwork and payment. Then we reviewed the bulldozer plan, we discussed which area to level, how deep, and where to push the soil and dirt. They only had a bulldozer on site and said they wouldn’t actually be getting the excavator in that day. It was busy on another job, presumably with another brother? Most of the home is slab on grade, so we still needed to level the site today. But we would need to wait to excavate the basement portion until next Thursday. However, this backed up my schedule because the footings guy was scheduled for next Thursday… I called and canceled the footings, but then at the end of the day, we found out that the excavator will be available by noon tomorrow, so maybe we are back on track? I won’t call the footings contractor back until I know for sure.
On the one hand, my lot is sandy, so it was pretty easy to work with… On the other hand, there was a lot of sand to work with. There was a dip in the middle of the site. We need to go down to undisturbed earth for the footings, so we couldn’t just fill in the dip. Instead, the bulldozer had to get everything down to that lowest level. They setup a laser level at a certain height and then a device in the dozer would tell Marty if he was too high, too low, or just right. I think it took longer (and more work) than Marty was expecting, so it is a good thing that I was on a fixed bid. But Marty was good about it and went out of his way to do a great job. He even cleaned up the driveway slope at the end of the day.
While the bulldozer was busy doing his work, I was busy putting in a couple hundred feet of silt fence. I don’t expect any erosion, but it is a requirement of my “soil erosion permit” and the 60$ worth of silt fence and a few hours of manual labor are better than the $2500 fine for not putting it up. The boys helped a bit. They spent most of their lives hearing that this house was coming, so we took them out of school for the day so they could see the ground breaking. I got some pics of them helping with the silt fence, but it is on Sherri’s camera and I am too tired to upload them now. Instead, here are some fun ones I snagged with my cell phone.
My younger boy is a bit of a Ham.
They really enjoyed playing in the dirt pile during a break.
We have a Bulldozer on the property!
It is just sitting there, very peaceful. I didn’t see any broken ground, but it is still pretty significant. There was also some mystery to it because we had not actually hired anyone or setup a start date yet. I had called Roe Brothers Excavation company a few times trying to ask them when it would be a good date for them to start. I had left several voice mails and emails, but not heard back at all… I assumed they were taking the whole week off (it is a holiday weekend here in the USA).
I have heard of sending messages by bottle or with smoke rings or even, in extreme cases, with bullets, but this was a dozer message. I called them up and cleared up the miss communication. They had planned to start first thing Tuesday morning (Monday is a holiday).
A catch… In our state, you are supposed to call “Miss Dig” before you dig. They mark all the buried wires and pipes. Sherri had already called them, but with the holiday weekend ahead, they said they might not get out there until Tuesday or Wednesday next week… There are power boxes strung along the roads, so I am pretty sure I already know what they will tell me. There are almost certainly lines buried under where the drive way will cross, but only right by the road. There shouldn’t be any lines under the home site, which is essentially in a corn field. The excavator says he only needs to go down a few inches for the driveway and the wires and gas pipes are located at least 2 ft below that.
Another catch, we haven’t actually closed on our loan yet (see the hurdles from a few days ago)… We don’t even have a closing date yet, but we are close enough that I am willing to go ahead anyway just to avoid losing more of the summer.
The weather forecast isn’t being very helpful either. They are calling for thunderstorms for most of this week. Next week, I am going to Washington state to visit Boeing (for work), so that won’t be good either… Anyway, I hope to post that we broke ground soon.
In the end, we setup a start date of Wednesday morning. ;^)
Picked Up My Building Permit…
I was only visiting the property because we were required to post a sign with our address and the permits clearly displayed. This is to help the inspectors find your lot. I picked up the “official” plans along with the permit. These need to be kept on site also, but probably not until things really get rolling.
The inspector had written notes on the plans, but fewer than I had expected. A couple were not a problem. For instance, he wants me to make sure that the ducts under my floors slope to an accessible point and to make sure that I have a good system of french drains. These were things that I planned to do, but were not spelled out clearly enough in the plans.
A few of the other notes don’t go as well with my unusual construction and I will try to talk to him about those over the next weeks.
The biggest issue was that he didn’t like my Frost Protected Shallow Footings. I sent him info on the ICC (International (building) Code Council) and ASCE (American Society of Civil Engineers) outlining how to properly apply this method. Hopefully he appreciates that because I planned to offset the additional cost of insulation with the reduced cost of shallower footings.
Another smaller issue was the specification of a “concrete encased electrode” in the foundation (aka Ufer ground). He probably recommended it because he could see how much rebar I already had in my foundation, and it is probably a good idea to tie my grounding system into all of that (although there have been cases when lightning strikes actually cause the moisture in the concrete to rapidly expand, crack and occasionally explode). Normally, a concrete encased electrode is a very effective grounding system and the NEC allows it to be used as your only grounding, but since my umbrella will be keeping my foundation very dry, it will not conduct electricity as effectively, I will probably still want to include more traditional grounding rods outside of my umbrella perimeter and also tie my ground wire into my well casing.
The inspector also added a number of additional inspections for the footings, arch placement, etc. including some “special inspections by a third party” for my arches (I assume before each is poured), my rebar and my shotcrete. I have no idea how these “third party inspections” will work, or who will do them, but I am guessing they won’t be cheap… I still need to talk with the inspector about it.